# PR-37 Delivery Planning — Reference
> Sprint Plan / Release Plan / Batch Plan / Capacity Plan / Roadmap Alignment
---
## Sprint Plan (Part F)
### Input
```js
generateSprintPlan({
stories, // SF-02 user stories
dependencies, // SF-02 dependency graph { nodes, edges }
priorities, // SF-02 priority entries [{ itemId, category, score }]
config, // { sprintDurationWeeks, teamVelocity, maxStoryPointsPerSprint }
})
```
### Output
```js
{
sprints: [{
sprintNumber: 1,
sprintGoal: "Sprint 1: 浏览用户注册列表 / 查看用户注册详情 / ...",
startDate: "Week 1",
endDate: "Week 2",
storyIds: ["us-1", "us-2", ...],
totalStoryPoints: 20,
epicIds: ["ep-1", "ep-2"],
featureIds: ["ft-1", "ft-2", "ft-3"],
criticalPath: ["us-1"],
risks: []
}, ...],
metrics: {
totalSprints: 6,
totalPoints: 138,
avgPointsPerSprint: 23,
estimatedDurationWeeks: 12
},
unplannedStories: [],
warnings: []
}
```
### Algorithm
1. Filter Must Have → Should Have → Could Have stories
2. Build dependency map from edges: `edge.from depends on edge.to`
3. Topological sort: Kahn's algorithm, deps come first
4. Assign to sprints by capacity (maxStoryPointsPerSprint / teamVelocity)
5. Dependency constraint: dependent story cannot be in earlier sprint than prerequisite
---
## Release Plan (Part G)
### Input
```js
generateReleasePlan({
mvpScope, // SF-02 MVP scope
priorities, // SF-02 priority entries
dependencies, // Dependency graph
stories, // User stories
epics, // Epics
features, // Features
})
```
### Output
```js
{
releases: [
{
version: "1.0.0",
name: "MVP — 最小可行产品",
features: { epicCount: 2, epicNames: [...], featureCount: 2, featureNames: [...], storyCount: 10, storyPoints: 30 },
description: "...",
releaseGoals: "...",
validationGates: ["All ACs pass", "Regression test pass", "Performance benchmark meet", "Security scan pass", "UAT sign-off"],
dependencyCheck: { unresolvedIds: [], allResolved: true },
releaseDate: "Week 8"
},
{ version: "1.1.0", name: "MVP Polish", ... },
{ version: "2.0.0", name: "V1 — 第一完整版本", ... },
{ version: "3.0.0", name: "V2 — 功能增强版本", ... },
{ version: "4.0.0", name: "Global — 全球化版本", ... }
],
warnings: []
}
```
---
## Batch Plan (Part H)
### Batch Types
| Batch Type | Description |
|------------|-------------|
| DevelopmentBatch L0 | 无依赖,可并行开发 |
| DevelopmentBatch L1 | 依赖 L0 完成 |
| DevelopmentBatch L2 | 依赖 L1 完成 |
| DevelopmentBatch L3+ | 深层依赖 |
| TestingBatch | 开发完成的进入测试 |
| ReleaseBatch | 测试通过的进入发布队列 |
| DeliveryBatch | 最终客户交付批次 |
### Output
```js
{
batches: [{
batchId: "batch-dev-l0-1",
batchType: "DevelopmentBatch",
name: "Development Level 0",
storyIds: ["us-1", "us-7", "us-13", ...],
featureIds: [...],
epicIds: [...],
parallelGroups: [["us-1", "us-7", "us-13"], ["us-19", "us-25"]],
prerequisiteBatches: []
}, ...]
}
```
---
## Capacity Plan (Part I)
### Configuration
```js
{
teamSize: 5, // 团队人数
velocity: 20, // 每 Sprint 完成点数
availabilityFactor: 0.8, // 可用率(扣除会议/假期)
complexityFactors: {
high: 2.0, // 高复杂度工作量倍率
medium: 1.0, // 中复杂度
low: 0.5 // 低复杂度
},
riskBufferPercent: 20 // 风险缓冲百分比
}
```
### Output
```js
{
totalEffort: 60, // 复杂度调整后总工作量(pts)
totalCapacity: 240, // 团队总容量(pts)
capacityUtilization: "25%",
sprintBySprint: [{
sprintNumber: 1,
capacity: 16,
allocated: 20,
utilization: "125%",
overCapacity: true
}, ...],
riskAdjustedEffort: 72,
deliveryForecast: {
optimistic: "Week 8 from project start",
realistic: "Week 10 from project start",
pessimistic: "Week 12 from project start"
},
resourceRecommendations: [
"Sprint 1 is over capacity. Consider adding 1 team member or splitting stories."
],
warnings: [...]
}
```
---
## Roadmap Alignment (Part J)
### Algorithm
1. **Phase Coverage**: 每个 Roadmap Phase 是否被 Release Plan 覆盖
2. **Story Coverage**: MVP/V1 Stories 是否被 Sprint Plan 完整分配
3. **Timeline Consistency**: Sprint 总周数是否在 Roadmap 时间范围内
4. **Budget Alignment**: Phase 预算与实际 Story Points × $/pt 是否一致(偏差 < 20%
5. **Dependency Integrity**: Dev→Test→Release→Delivery 批次链是否完整
### Output
```js
{
overallVerdict: "aligned", // "aligned" / "partial" / "misaligned"
alignmentScore: 85, // 0-100
phaseCoverage: { ... },
storyCoverage: { ... },
timelineCheck: { ... },
budgetCheck: { ... },
dependencyCheck: { ... },
warnings: [...],
recommendations: [...],
summary: "## Roadmap Alignment: ALIGNED (85/100) ..."
}
```
---
## Factory Integration (Part K)
### Full Pipeline
```
SF-01 (Strategy) → SF-02 (Requirements) → PR-37 (Delivery Planning) → SF-03 (Design)
│ │
┌──────┘ ┌───────────┴────────────┐
│ │ │
Domain Intelligence Delivery Planning
│ │
┌────┴─────┐ ┌───────┼───────┬──────────┐
Classifier Epics Sprint Release Batch Capacity → Align
│ │ Plan Plan Plan Plan Report
│ Features
Validation Validation
```
### API
```js
// Domain Intelligence
const di = createDomainIntelligenceFactory(
{ productName: "ERP系统" },
{ domainOverride: null, includeValidation: true }
);
// → { classification, epics, features, validation }
// Delivery Planning
const dp = createDeliveryPlanningFactory(
sf02Output, // upstreamArtifacts from SF-02
{ sprint: { teamVelocity: 20 }, capacity: { teamSize: 5 } }
);
// → { sprintPlan, releasePlan, batchPlan, capacityPlan, alignmentReport }
```